If You plan to consume over 15 mill. m3 of gas per year or require a daily distribution capacity above 100,000 m3 per day, it is likely that the connection of Your off-take point to the distribution network will require a substantial investment in order to adapt or extend the distribution network.
This will be confirmed by a Pre-feasibility Study, which you can order from SPP - distribúcia, a.s. free of charge.
This study, accounting for the expected location and distance of Your prospective off-take point from our network and the expected consumption parameters, will confirm the feasibility of the connection, especially the costs that will be incurred by adaptation or extension.
The estimated costs do not exceed the amount of EUR 1 mil.
The estimated costs exceed the amount of EUR 1 mil.
In case of any questions please do not hesitate and contact us at SPP – distribúcia, a.s. Mlynské Nivy 44/b, 825 11 Bratislava 25, Distribution Marketing.